a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take to paint the house?

Respuesta :

Einstein08 Einstein08
  • 01-09-2018
it will take 4 days to paint the house with 5 men
Answer Link
tramserran
tramserran tramserran
  • 01-09-2018

1 house = 6 men x 5 days  = 30 man days

Need 30 man days with only 5 men: 30x = 5 men   →  x = 6

It will take 6 days for 5 men to complete the job.

Answer: 6 days


Answer Link

Otras preguntas

Which statement explains an economic outcome of international trade? Competition is erased within the global marketplace. Imports and exports move around the wo
a. "The choice of strategy for a multinational firm must depend on a comparison of the benefits of that strategy (in terms of value creation) with the costs of
What is the slope of the linear represents by the equation y = 4/5 x -3
8/12 - 1/3 = Please answer my question
Where did the Nazis carry out most of the murders that were the main part of a final solution? A. In death camps B. In slave labor camps C. In ghetto D. In Poli
What was a consequence of Julius Caesar assasination
When President Bush got together with his advisers to discuss going to war with Iraq, no one wanted to disagree with his wish to begin bombing. This is an examp
who does scout sit on the porch and talk with about the radleys ?
the ratio of 2.5 meters to 80 centimeters can be written in form 1: n find the value of n n=
25% of what number is 225?